activities moving with data date line
In the Open Standard
Jonathan WardMember for 19 years 8 months
- Created
- 6
- 2
0
Good Afternoon,
i could well be asking a glaringly obvious question,,,
i would like to (F9) my current schedule on a daily basis, i do NOT want activities that have not started i.e been progressed, to move in-line with the data date line, i would like these activities to stay where they currently are placed while the data date lines moves on past them,, is this possible??
once again
many thanks
jon
i could well be asking a glaringly obvious question,,,
i would like to (F9) my current schedule on a daily basis, i do NOT want activities that have not started i.e been progressed, to move in-line with the data date line, i would like these activities to stay where they currently are placed while the data date lines moves on past them,, is this possible??
once again
many thanks
jon
6 replies
Oldest firstLog in or join to reply