can anybody tell me what is the logic limit for the total float of any activity ?
and also what the precentage of the activities to be critical in project about 3000 activities

3 replies

Oldest first
  1. 0
    Amreshwar Shukla ·
    Can you explain your question little more ??

    Rgd
  2. 0
    Ersin Namli ·
    The max limit of total float of an activity is the remaining duration of project after the activity finished.
  3. 0
    Santhosh kumar Narayanan ·
    There is no max or min limit for total float. Depends the logic links. the same is applicable for max % of activities in critical path!!..