P3 on Web

Renjith BMember for 20 years 11 months
Created
1
1
0
Hi friends,

I am using tabular reports as web pages on our intranet for references by all departments. Is it is possible to add graphical reports to HTML by using Web Wizard

Thanks in advance

1 reply

Oldest first
  1. 0
    Andrew Podolny ·
    Hi there.
    Yes it’s possible but a little bit tricky.
    1. Prepare the report through Tools-->Graphic Report
    2. Save this file from P3 Look as PDF, JPG, etc (I’m using Ghostscript PDF writer)
    3. Create a Report in P3 Web Publishing Wizard using an existing file of any type.
    4. Point at your PDF file.

    Regards,
    Andrew