Adding Ramzan (Hourly) calender into P3

A DMember for 19 years 5 months
Created
6
3
0
Hi,

I have prepared a schedule for 30 months with planning unit as DAYS. Now, i have been instructed by my PM to consider only 4 working hours during the ramzan month (4 weeks) against 8 hours during rest of the period.

In these four weeks, productivity for most of the items will be reduced by half.

So, can I add one more calender as planning Unit - HOUR, when i have already allocated calender with planning unit as DAY.

Any advise?

Raviraj

6 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    Hi Ravi,

    The answer to your question is NO you cannot add one more calender as planning Unit - HOUR, when you have already allocated calender with planning unit as DAY.


    You can try making a Calendar with equivalent working days (3 instead of 6). This may help to some extent.

    Regards,

    Ashraf
  2. 0
    Alexandre Faulx-Briole ·
    Hi Ravi & Ashraf,
    I have just given the same advice to one customer in Algeria: create a "Ramadhan" daily calendar where every other day is a nonworking day.
    You can only create calendars with the same unit as the project planning unit.
    mâa salama
    Alexandre
  3. 0
    Ashraf Jahangeer ·
    Hi Alex/Ravi,

    Have you tried copying this project with HOURS as planning unit. I hope if it works the solution will be much simple.


    Regards,

    Ashraf
  4. 0
    A D ·
    Thanks Ashraf for the immediate response given.

    This doesn’t work, but yaa as alex said i have to show every alternate day in ramdan month as non-working, which is not correct logically, but thats the only solution.

    Cheers,

    Raviraj
  5. 0
    Alexandre Faulx-Briole ·
    ashraf,
    for sure planing the project in hours instead of days would be more simple, but it does not sound logical for every one to plan a 30 month project in hours, don’t you agree?
    bqa 3ala kheir
    Alexandre
  6. 0
    Ashraf Jahangeer ·
    Hi Alex,

    You are very correct if the total duration is in weeks then we should plan in hours e.g.shutdowns etc.


    Regards,

    Ashraf

Log in or join to reply