Adding Ramzan (Hourly) calender into P3
In the Open Standard
A DMember for 19 years 5 months
- Created
- 6
- 3
0
Hi,
I have prepared a schedule for 30 months with planning unit as DAYS. Now, i have been instructed by my PM to consider only 4 working hours during the ramzan month (4 weeks) against 8 hours during rest of the period.
In these four weeks, productivity for most of the items will be reduced by half.
So, can I add one more calender as planning Unit - HOUR, when i have already allocated calender with planning unit as DAY.
Any advise?
Raviraj
I have prepared a schedule for 30 months with planning unit as DAYS. Now, i have been instructed by my PM to consider only 4 working hours during the ramzan month (4 weeks) against 8 hours during rest of the period.
In these four weeks, productivity for most of the items will be reduced by half.
So, can I add one more calender as planning Unit - HOUR, when i have already allocated calender with planning unit as DAY.
Any advise?
Raviraj
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?