Pre CPM versus Post CPM
In the Open Standard
Ulysses GarciaMember for 21 years 1 month
- Created
- 2
- 3
0
Hi Planners,
Want to know your golden ideas about this subject.
1.Post CPM - is a critical path derived from a manual computation ( ie. forward and backward pass)
2. Pre CPM - is already pressumed that critical activities will run through this path.
In item 2.This method is usually used using todays powerful software in which i believed will severely violate the concept of planning not to mention the mind of the original inventor of CPM.
Regards...Uly
Want to know your golden ideas about this subject.
1.Post CPM - is a critical path derived from a manual computation ( ie. forward and backward pass)
2. Pre CPM - is already pressumed that critical activities will run through this path.
In item 2.This method is usually used using todays powerful software in which i believed will severely violate the concept of planning not to mention the mind of the original inventor of CPM.
Regards...Uly
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?