MPP to P3

Raiez MoideenMember for 19 years 4 months
Created
1
1
0
Its not working when I assign relations to the activity with activity type WBS, just as assigning relations to main tasks in MPP. Please tell me a solution.
Or else pls suggest me a way to show main tasks and sub tasks as in MPP, where a main task can have relation with with other main tasks or sub tasks in other main tasks.

1 reply

Oldest first
  1. 0
    Paul Harris ·
    A WBS activity spans the duration of all activities with the same WBS code. It is not intended to assign relationships to a WBS activity.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au