Loading of resources

Rick AquinoMember for 21 years 6 months
Created
2
1
0

Dear All,

If you have an equipment in ur resources using the units "each" (not hrs), what is the correct way to load it in my resources? do i have to use 1 each or 10 hrs (units/day), what is the effect if i’m going to use hrs when in fact i used "each" in my data base. i’m a little bit lost in my Budgeted quantity.

Note: if 1 machine stays for 10 hrs in 5 days, what unit i’m going to used 1 each/day or 10hrs/day.

Thanks

Rick

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    i presumed the calculations are linear, please note of your planning unit first, if it is in Day or Hour; then your resource budget quantity; also note that your budget quatity will be distributed linearly; so whether or not you use "each" or hour, expect that it will be calculated linearly, so it’s up to you to determine which one is workable!
  2. 0
    Rick Aquino ·


    Dear Anoon,

    Ah ok, Thank you very much for your quick reply.

    Regards,

    Rick