Loading of resources
In the Open Standard
Rick AquinoMember for 21 years 6 months
- Created
- 2
- 1
0
Dear All,
If you have an equipment in ur resources using the units "each" (not hrs), what is the correct way to load it in my resources? do i have to use 1 each or 10 hrs (units/day), what is the effect if i’m going to use hrs when in fact i used "each" in my data base. i’m a little bit lost in my Budgeted quantity.
Note: if 1 machine stays for 10 hrs in 5 days, what unit i’m going to used 1 each/day or 10hrs/day.
Thanks
Rick
2 replies