DISPLAYING HOLIDAYS ON BAR CHART

Zameer JeffMember for 19 years 5 months
Created
2
1
0
I have plugged in Government holidays in the global calander. Do I have to do another step to assign these holidays as I want to display Government holidays on my bar chart. Could any one help me to explain step by step that how can I sow holidays on the bar chart as non working days.So when i take a print out of schedule or 3- Week lookahead schedule i can see holidays on the print out of bar chart.

Thanks

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    there is necking; or you can include logs as bar labels specifying the holidays
  2. 0
    A D ·
    Hi zameer,

    As anoon said, go to Format --> Bars and then in the defined bar area, tick the checkbox in the neck column

    Easy