Filtering Negative lag

Rahmat HidayatMember for 24 years 2 months
Created
5
4
0
I’ve Boss more crazy now, he ask me to filter all activities with FS negative lag. How to do that best in P3 ? but pls don’t ask to do that manually ’coz I’ll be crazy also.

Thx in advance if u r genius.

5 replies

Oldest first
  1. 0
    Ulysses Garcia ·
    You can give a list of lag to your boss in other option, using report then tabular; this will give you list of lags.
    maybe in some software you can filter lags, but in p3 in wont.
  2. 0
    Rahmat Hidayat ·
    Oh ulysses..it means thousands of lags like sands in the beach. U know after that I have to change those negative lags to ss&ff positive lags. I hope this problem not happen to u :[). Anyway thanks a lot for your input.

    I love Qatar.
  3. 0
    Dattatreya Padharthi ·
    Hidayat,

    pl export all the successor relationship in the export feature in either dbf or\excel. You will get a list of all activities with successor , lag duration & type of relation ship. You can filter all negative lags. As for other details like title & codes, export the normal activity content in a separate file & link/marry these two files & produce whatever report you boss wants. I have just re-checked the procedure & it works well.

    Cheers
    Dattatreya
  4. 0
    Ulysses Garcia ·
    Rahmat,

    Are you contractor or client side, who make this lags?

    Also, are you trying to change lag to + ?, you do not mentioned it in your 1st original question..

    make it clear what do you want to do
  5. 0
    Rahmat Hidayat ·
    Thanks DATTATREYA I get the point. I ’ll try to filter them in Excel and marry them using lookup function. U r right it must be easy to change any relationships there in Excel as we want. After that I’ll try to re-import.I believe u r one of P3 masters.

    Hi ulysses, I’m Contractor and also Client of our Subcontractors. My friend make that (-) lags before he go, so risk on me now..lol. I’m sorry dude the original question is not clear for u. Enjoy in Qatar, I think it’s good and safe country like Japan.

Log in or join to reply