pls help me in cost loading

Sinan FahmiMember for 19 years 10 months
Created
4
1
0
hi all
i assign bugdet cost for each activities in my project and after i run cost loading report i found defrent cost showing to me for example
i have a round 100 activites for concrete work and the summary bugdet cost for concrete work should be 8504750, but after running cost load the bugdet for this item showing 1035400. and other summary came less than budet...

please help me in this matter

4 replies

Oldest first
  1. 0
    Anoon Iimos ·
    do it in excel!
  2. 0
    A D ·
    Anoon, thats d best solution.

    BTW, check ur resources. Have u done any global change and put cost units into resources, which are used somewhere else....

  3. 0
    Sinan Fahmi ·
    please can you explain more...
  4. 0
    Kamarul Bahrin Hassan ·
    hi sinan

    i think you batter check on cost. click f7 and check all your cost. resource, cost to complete, cost variance. i quess you miss overthere.

Log in or join to reply