ACTICITY ID IN PRIMAVERA 3.1V

Rajendra PrasadMember for 19 years 2 months
Created
1
1
0
HOW TO DEFINE IN DICTIONARY AND ASSIGN

1 reply

Oldest first
  1. 0
    Brennan Westworth ·
    I assume you are refering to activity ID codes,

    These are created in Data>Activity Codes, then select the "Activity ID" tab.

    You then define codes based on the structure of your activity ID. by default the first two characters are for your sub-project ID, you might then define one for each separable portion and then another for the phase.

    The activity ID activity codes are not assigned to activities like conventional activity codes, but p3 derives them from the makeup of your activity ID.

    EG: activity id AA1C0010 could be Subproject AA, Separable portion 1, Construction phase, activity 10.


    hope this helps