changed the WBS :locate activities with old WBS values

Pranab Kumar DebMember for 19 years 8 months
Created
4
4
0
Hello Freinds,
I changed the WBS of a project , now some of the activities which are assigned the previous WBS codes i am unable to locate please can you advise me how i can find activities which have WBS not defined in the WBS dictionary.
Regards
deb

4 replies

Oldest first
  1. 0
    Steven Oliver ·
    In your WBS view, use a spare Activity Code field as a column, and fill this with a value.

    Switch to activity view, and with the same column diplayed. Any activity which does not have an entry in the Activity Code field doesnt match the WBS ( I Think !)
  2. 0
    Ferdinand U. ·
    Gchange if WBST eq " " then WBS eq DELETE
    then filter all activities WBS eq (no value)

    take note: you must be in WBS organized layout when you filter...
  3. 0
    Ferdinand U. ·
    mistake...should be --- you must NOT be in WBS layout when you filter
  4. 0
    Pranab Kumar Deb ·
    thanks ferdinand and oliver , that were excellent ideas.
    now while in my wbs layout (with all activities filter) there are 1527 activties , where as when i sort by project i get 1531 activities , i dotn know where the 4 activities go in wbs layout.
    regards
    deb