Quantity details in Primavera
In the Open Standard
Anand DominicMember for 20 years 6 months
- Created
- 6
- 2
0
Iam a planner responsible for E&I works. As a sample a portion of my plan has the following activites
Cable Tray Support Fabrication
Cable Tray Support Installation
Tray Installation
Till i date i have only entered manhours (Resource) required for each of these activites in Primavera Schedule (P3).
The actual & contractual quantities for these activities (tons & Meters) was monitored in a Spreadsheet.
Is there a method of monitoring these quantities (different unit of measurements tons, meters, Nos., cum etc) withing the P3 schedule itself.
Happy Planning..
Cable Tray Support Fabrication
Cable Tray Support Installation
Tray Installation
Till i date i have only entered manhours (Resource) required for each of these activites in Primavera Schedule (P3).
The actual & contractual quantities for these activities (tons & Meters) was monitored in a Spreadsheet.
Is there a method of monitoring these quantities (different unit of measurements tons, meters, Nos., cum etc) withing the P3 schedule itself.
Happy Planning..
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?