P3
In the Open Standard
Ranganathan RangaswamyMember for 19 years 2 months
- Created
- 4
- 1
0
I have one doubt in P3
I have got estimated labour hours for eg 1000hrs
and have duration for eg 10 days
If i use activity form RES tab and go to Budgeted quantity and enter 1000hrs then units per day becomes 100hrs.
which is 1000hrs/10days =100hrs
If the people work 10hrs per day then thenumber of people required for that work is 10 peoples. How to get the number of people??
where we have to enter the 10hrs working time? I have opened the file using planning unit as day. Is it that i have to enter in the resource directory normal limit as 0 and maximum limit as 10
pl guide me
I have got estimated labour hours for eg 1000hrs
and have duration for eg 10 days
If i use activity form RES tab and go to Budgeted quantity and enter 1000hrs then units per day becomes 100hrs.
which is 1000hrs/10days =100hrs
If the people work 10hrs per day then thenumber of people required for that work is 10 peoples. How to get the number of people??
where we have to enter the 10hrs working time? I have opened the file using planning unit as day. Is it that i have to enter in the resource directory normal limit as 0 and maximum limit as 10
pl guide me
4 replies
Oldest firstLog in or join to reply