error message: Unable to create Temporary file

Mangesh KhuspeMember for 19 years 6 months
Created
4
2
0
Hi
all,
i am trying to schedule a project in p3 and it is giving me error messgae
Unable to create temporary file , Possibly out of disk space.
what does it mean as there is large amount of space available on disk.

regards

mangesh

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Mangesh
    Do you have appropriate access rights under Window? Temporary files will be written into a certain directoy - in general under P3WIN. You’ll need the appropriate rights for this directory.
    Regards
    Dieter
  2. 0
    Mangesh Khuspe ·
    Hi
    dieter well i do not have proper access rights under windows but these files are not located on c drive, they are located on main server.
    but if i guess that the temporary files are stored in p3 directory and not having proper rights will not schedule the project, am i right.

    cheers

    mangesh
  3. 0
    Mk Tse ·
    if the temp file directory is located on server, please allow every user have his own temp file directory. Some the temp file may be in same name, if one user already "point" to that file, others may have trouble.
  4. 0
    Ashraf Jahangeer ·
    Hi there,

    Please check that your project is being saved in sub sub sub directory.

    Primevera has a limit for this make a new directory in root and try to save it there.

    Regards,


    Ashraf

Log in or join to reply