Resources in Primavera Suretrak

Ernesto PuyanaMember for 25 years 9 months
Created
5
4
0
Suretrak users out there, Please help me:

I’m working on a 2700 activity project. When I assign resources, after a certain number of assignments, the program crashes.

Is there a limit to the number of resources I can assign to a project? How many?

Or is there a limit to the number of resource assignments I can make.

Is there a way around this? would project groups help me?

I’ll appreciate any advice, since I don´t have a P3 at hand.

5 replies

Oldest first
  1. 0
    David Kelly ·
    Do you have the latest service pack?

    YOU MUST USE PROJECT GROUP FORMAT!!
  2. 0
    Ernesto Puyana ·
    Thanks for input.

    Yes I have the service pack (3.0b) and I always use project groups. I think I already found solution to my problem: I though i was getting kicked out by the software because of some capacity limit, but actually, i was generating a conflict since i by mistake uploaded the same resource code to different activities with different units of measure. That generated a conflict.

    Thanks again.

    Ernesto
  3. 0
    Dennis Hanks ·
    For what it is worth: I believe there is another service pack (c). I am patched to 3.0c. If I remember correctly it came out about 10-12 months ago.
  4. 0
    Ernesto Puyana ·
    That’s good news. Didn´t know about, and haven´t seen it in Primavera.com. Do you know where else it would be available?
  5. 0
    Dennis Hanks ·
    My maintenance agreement has lapsed, so I cannot check the Primavera website. It should be there.