Numerical Overflow ?

David MosesMember for 21 years 11 months
Created
2
2
0
Hi There,

While I was loading resources and budgeted quantities to my schedule, P3 gave me this message;

"Some costs have not been calculated due to numerical overflow"

What is that? Any idea?

Regards

2 replies

Oldest first
  1. 0
    David Kelly ·
    If you use decimal places , the biggest number you can have (even if its a roll-up) is 2billion (i think)


    Switch decimal places off and see if you still get the error
  2. 0
    David Moses ·
    Hi There,

    Here is the solution for that problem,

    Primavera Project Planner Help:
    Add a new project
    Item 6: In the decimal places field, select the number of decimal places to use for resource and cost data. If costs in your project exceed $100 million for a summary group, change the decimal-place configuration to 0.

    I did it accordingly, then "All costs have been calculated".

    Regards

Log in or join to reply