.PDF not generating all data (various Headers r lost)

Seng FatsuraMember for 21 years 7 months
Created
3
2
0
I have a P3 user who is complaining about generated .pdf files of projects not containing all headers that the project has. I’ve created a new ’pdf’ port in his printers so it’s generated at C:PDFPort, which fixed the problem of p3 locking up while generating the .pdf, but i’m not sure what is causing some (usually sporatic) data not to be generated in adobe.

Any help or suport would be GREATLY appreciated.

3 replies

Oldest first
  1. 0
    Paul Harris ·

    Have you loaded the latest service pack? It is number 3.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Seng Fatsura ·
    Yes. I have reinstalled, and installed the SP3, created the new PDF port, but it is still happening. User (and P3 manager) thinks its a memory issue, but he has 512mb RAM...?
  3. 0
    Johny Kesserwany ·
    Try the pdf995 it’s working good with Primavera products.

    http://www.pdf995.com/ and download pdf995 it’s free. After installing it will create a printer called PDF995.

    JK