Hi Planners

I am new to the planning world. can someone tell me where I could find the Deffinitions for abbreviations such as ASW,QAC,LFW,ORBC, AFW,RUT,AQ,BC,BQ,ACC,LCOND......ETC.



Cheers

Nigel


1 reply

Oldest first
  1. 0
    Ronald Romero ·
    Nigel,

    BC= Budgeted Cost
    BQ= Budgeted Quantity
    ORBC= Original Budget Cost which is a customize data
    QAC = Qauntity at Completion
    ACC = Cost Account
    Some are defined in the Global Change variables others in the glossary

    Some definition are unique in primavera others are user’s defined and you can also make one as your own.

    Cheers