grey area in timescale

Jonathan WardMember for 19 years 8 months
Created
2
1
0
once again, any help would be much appreciated, could anyone adivse on how i get a set grey area from 2 set dates in my timescale?
many thanks
Jon

2 replies

Oldest first
  1. 0
    A D ·
    Hi,

    Go to Insert --> Object.

    A small pop-up window will appear with six symbols. The two symbols with break line are used to show grey line between the two set areas.

    Just click on the symbol and then drag the point to the desired date. Those two symbols will give you option to choose a density of the grey area.

    Cheers,

    Ravi
  2. 0
    Jonathan Ward ·
    thats great, many thanks