I thought I understood Total Floats
In the Open Standard
Brian ChanMember for 19 years
- Created
- 3
- 2
0
Ok,
I’ve got a task called LTC. Its successor is Dirt Excavation with a FS relationship, 0 lag.
Now, the TF of both activities are showing as 48.
I’ve tied the completion of LTC with a Finish Milestone, and then I’ve tied that milestone into Dirt Excavation with a FS, so that it’s got a successor.
The finish milestone somehow shows a TF of 33. Shouldn’t it be 48 since it is sandwiched between the 2 TF=48 activities?
What’s wrong here?
I’ve got a task called LTC. Its successor is Dirt Excavation with a FS relationship, 0 lag.
Now, the TF of both activities are showing as 48.
I’ve tied the completion of LTC with a Finish Milestone, and then I’ve tied that milestone into Dirt Excavation with a FS, so that it’s got a successor.
The finish milestone somehow shows a TF of 33. Shouldn’t it be 48 since it is sandwiched between the 2 TF=48 activities?
What’s wrong here?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?