Curves Early and Late

Felipe N GMember for 18 years 6 months
Created
1
1
0
Hello All,

I am new in the forum and i wish to know how can i obtain the values to plot the Early and Late Curves?

I do the next in P3:

TOOLS\TABULAR REPORTS\RESOURCE\TABULAR and choose RT-01 "Tabular Resource Use - Weekly - FieId Engineer" to generate the values the early and late curve

Is´t ok? or is there other way?

thank All

Regards,
Felipe

1 reply

Oldest first
  1. 0
    Ulysses Garcia ·
    felipe,

    you may use wildcard to trace a curve of all resources

    Uly