High float

Mark BandongMember for 18 years 6 months
Created
2
1
0
Hello everyone!
I am new to p3 and i need help. The float in my programme is descending. The float in the beginning of the project is high and the float at the end is zero already. I checked the network logic and it seems to be fine. I just don’t know where i missed. Tasks with the same description has a closed network logic. I used FS,SS and FF relationship in each tasks per category. The last activity is linked to the constrained finish milestone. The first task is also link to the start milestone. What are the other means of checking network logic and floats? Thanks.

Regards,
Den

2 replies

Oldest first
  1. 0
    Kieran Thomson ·
    Morning Denmark (and the rest of the world!)

    Do you have any intermediate constraints in the programme ie. delivery of materials start on dates etc.
    Also check any open ended activities, especialy if you are using start to start logic.

    Regards

    Kieran
  2. 0
    Mark Bandong ·
    Hello Kieran

    I assumed to have unlimited resources.The only constraints i have is the issuance commencement of work and the completion of work. I used SS,FF and FS. Kindly elaborate the open ended activities? I’m really new in planning and i did not have any formal study in planning. Thank you.

    Regards,
    Denmark