Question about P3’s CPM algorithm
In the Open Standard
Stephen DevauxMember for 21 years 6 months
- Created
- 5
- 2
0
I think I know the answer, but just to be sure, would someone be kind enough to tell me what P3 computes for the duration of the following six-activity project?
A 10d No preds
B 10d Pred: A/FS0
C 10d Pred: B/FS0
D 5d Preds: A/FS0, B/FF5
E 10d Pred: D/SS5
F 10d Preds: D/FS, E/FS
Also, what is the critical path, and what would the project duration be if Activity D’s duration was 9d? 3d?
Since this issue is not specific to P3, I am also starting a thread to discuss it in the Planning, Scheduling and Programming Discussion.
A 10d No preds
B 10d Pred: A/FS0
C 10d Pred: B/FS0
D 5d Preds: A/FS0, B/FF5
E 10d Pred: D/SS5
F 10d Preds: D/FS, E/FS
Also, what is the critical path, and what would the project duration be if Activity D’s duration was 9d? 3d?
Since this issue is not specific to P3, I am also starting a thread to discuss it in the Planning, Scheduling and Programming Discussion.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?