Resourcing issue in P5
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 4
- 1
0
Hi, we are suing P5 and I have a big issue:
Please PLEASE help me out… I’m now going to put/assigning resources/roles to my project. The overall project has an agreed/contracted total amount of WORK of 236,000 hours having a milestone finished date for every main tasks.
- The project is a construction type having a FIFO (fly-in / fly-out) rosters for all the resources.
- Each resource have different FIFO rosters having a 3-weeks ON and 1-week OFF. So it means each resources has its own work calendar.
- Current total resources to be assigned are 50 electricians and 10 boilermakers.
- A task will have an assigned number of electricians or boilermaker working or only an electrician or only a boilermaker. For example a task has an assignment of 3 electricians and 1 boilermaker, but these 3 electrician and 1 boilermaker can be anybody (from the pool of 50 electricians and 10 boilermaker). The reason for this is that the supervisor can call an electrician or boilermaker assigned originally to Task A then transfer him to help on Task B. How complicated!!
- At the end of the day each electrician or boilermaker will enter into their timesheet (paper only) and put in the actual hours they worked and in what particular area or task was that.
1. Problem is how to assign a resource or a role in those specific tasks???
2. Should it be assigned by role or assigned by specific names of electricians/boilermakers! How can it be done?
3. How to review the resources? If we want to forecast how many more electricians or boilermakers to hire in the next few months to meet the milestone deadline, how can it be done?
So please help me out. Thanks.
Please PLEASE help me out… I’m now going to put/assigning resources/roles to my project. The overall project has an agreed/contracted total amount of WORK of 236,000 hours having a milestone finished date for every main tasks.
- The project is a construction type having a FIFO (fly-in / fly-out) rosters for all the resources.
- Each resource have different FIFO rosters having a 3-weeks ON and 1-week OFF. So it means each resources has its own work calendar.
- Current total resources to be assigned are 50 electricians and 10 boilermakers.
- A task will have an assigned number of electricians or boilermaker working or only an electrician or only a boilermaker. For example a task has an assignment of 3 electricians and 1 boilermaker, but these 3 electrician and 1 boilermaker can be anybody (from the pool of 50 electricians and 10 boilermaker). The reason for this is that the supervisor can call an electrician or boilermaker assigned originally to Task A then transfer him to help on Task B. How complicated!!
- At the end of the day each electrician or boilermaker will enter into their timesheet (paper only) and put in the actual hours they worked and in what particular area or task was that.
1. Problem is how to assign a resource or a role in those specific tasks???
2. Should it be assigned by role or assigned by specific names of electricians/boilermakers! How can it be done?
3. How to review the resources? If we want to forecast how many more electricians or boilermakers to hire in the next few months to meet the milestone deadline, how can it be done?
So please help me out. Thanks.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?