Linking Projects

Jineesh DathMember for 19 years 1 month
Created
1
1
0
Hi everyone,

I wish to know, if there is a way I can make a master programme which will have milestones only of different projects (about four independent projects)which while I update the other programmes will get updated automatically so that I know how much is the dealy in each project (if any) and the completion date. Or do I have to update them seperately?

What I require is all major milestones of all my projects in one summary sheet without having to update the programme twice.

It will be nice to see your replies at the earliest.

Thanks

Regards
Jineesh

1 reply

Oldest first
  1. 0
    Alex Wong ·
    Jineesh

    Assume u are using P3 3.1 - Since your posting is in this forum categories.

    All you need to do is to have a master project and 4 sub-projects and with a filter to filter our the critical milestone.

    The sub-project can be updated independent to the master program.

    HTH

    Alex