Critical Path in P3 w/o Longest Path

James BraghiniMember for 18 years 5 months
Created
2
2
0
Does anyone have a better way of creating a filter for a Critical Path without using the Longest Path? I have a job where the total job has negative float however some activities in the critical path string has positive float.

Thanks,
JJB

2 replies

Oldest first
  1. 0
    Ronald Winter ·
    You seem to infer that all activities listed as being on the critical path must have the same float in order to be a valid critical path. This was never a part of the definition of “critical path.”

    Many issues can cause the longest chain of activities to have different float; activity and resource calendars, interruptible activities, start versus finish float, and constraints come to mind immediately. For more on this, I suggest that you review a paper that I once presented titled, “Longest Path Value” on my website at http://ronwinterconsulting.com/published.htm. Good luck!
  2. 0
    Johny Kesserwany ·
    you can fix a number for the total float and the filter will display all activities having a TF less than this number...

    Total float LT (x)