Hi all,

Who know how I can export my calendar data to excel. Thanks to respond.

Cheers~

3 replies

Oldest first
  1. 0
    Mujahid Akhtar ·
    You can’t export Calenders to excel from P3 rather can print indivisual or all calenders in summarized or detailed form for the project showing working and non working durations.

    Chintoo
  2. 0
    Ashutosh Nema, PMP ·
    You can not transfer CALANDER Data from P3 to MS excel but you can transfer calander to another project in P3 or you can print it.

    Ashutosh Nema
  3. 0
    Ife Olyke ·
    Thanks Ashutosh.

    I can certainly print it in PDF, but I was wondering if I it’s possible to view it in text format, then it could be converted to excel and manipulated in excel...