P6 - Users tracking log
In the Open Standard
Carmen ArapeMember for 22 years 3 months
- Created
- 4
- 2
0
Hi All
Does anyone have an idea about Users tracking log in P6.
We built an EPC schedule split in 4 different schedules. One schedule is full dedicated to procurement. This is the heart of the 4 units for which 4 different schedules comprise Engineering and construction. The 3 planners have defined links between engineering – procurement – construction.
As we update on monthly basis, we experiment all type of errors such as: deleted links or link lag.
Does P6 have an option where someone can track what a planner has been doing in the procurement schedule (the heart of the EPC multi schedules).
Thanks & Cheers,
carmen
Does anyone have an idea about Users tracking log in P6.
We built an EPC schedule split in 4 different schedules. One schedule is full dedicated to procurement. This is the heart of the 4 units for which 4 different schedules comprise Engineering and construction. The 3 planners have defined links between engineering – procurement – construction.
As we update on monthly basis, we experiment all type of errors such as: deleted links or link lag.
Does P6 have an option where someone can track what a planner has been doing in the procurement schedule (the heart of the EPC multi schedules).
Thanks & Cheers,
carmen
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?