Converter P6 to P3

Santanu PurkayasthaMember for 18 years 5 months
Created
5
4
0
Dear all,

Good afternoon (indian time)

Can anybody reply back against my query ? I just want to convert my programme from Primavera P6 to P3

Is it posible ?

T/R

Santanu P.
Planning Cell

5 replies

Oldest first
  1. 0
    Paul Harris ·
    Use the P6 export function to convert it from P6 to P3 format.

    If the file is in XER format you might have a problem, but then of course you could always open it with Asta Powerproject and save in P3 format, or import it into a Primavera database and export.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  2. 0
    Ashutosh Nema, PMP ·
    You can use export function to convert P6 project to P3. It is very easy.

    Ashutosh Nema
    Dar Al Handasah
  3. 0
    Santanu Purkayastha ·
    Dear Ashutosh,

    Its Santanu from Delhi-India.

    Could you please tell me the path to do the same.

    Thanks for your kind co-operation
  4. 0
    Ashutosh Nema, PMP ·
    Soory for the delay
    Open P6.TO convert a particular project the same should be open.
    Select File-Export
    Selct P3 in export window-next-select same project
    Give name and location to the export project-next....
    Than follw the dialog box...

    Thanks
  5. 0
    Ezra Nyakundi ·

    I have uploaded a video

    I have uploaded a video demontration how to convert p6 to p3

    click here to watch

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?