Total Float (negative i.e. -1)
In the Open Standard
Santanu PurkayasthaMember for 18 years 5 months
- Created
- 0
- 1
0
Dear All,
So far as P6 concern.In my master construction programme i am getting a negative float viz, -1, -2 etc. in summary only.where as in activity it is showing zero float and all such cases are Critical Path.
What should I do ? can I go ahead with that one ?
Pl. discuss.
Santanu P.
Planning Cell
So far as P6 concern.In my master construction programme i am getting a negative float viz, -1, -2 etc. in summary only.where as in activity it is showing zero float and all such cases are Critical Path.
What should I do ? can I go ahead with that one ?
Pl. discuss.
Santanu P.
Planning Cell
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?