Constarints in Primavera

Daniel SitumorangMember for 23 years 1 month
Created
1
2
0
Hi all,
When applying contraints to a particular type of activity, are there any exclusions? I’ve recently imported a contractor’s schedule and experienced that a particular date (finish milestone) that has been given a ’finish on or before’ constraint, moved.
Appreciate any insights.
Thansk.

dts

1 reply

Oldest first
  1. 0
    James Braghini ·
    I would not use any contraint on the finish milestone. I would have the drop dead completion date placed in the Project Data.

    Good luck on you project.

    James B.