Hi All,

Could anyone tell me, what is SPI & CPI ?

3 replies

Oldest first
  1. 0
    Shaneouz Kallal ·
    Hi,
    SPI = Schedule performance index
    CPI = Cost performance index
    Please see details P3 manual or help.

    Shaneouz
  2. 0
    Arnold Puy ·
    Hi,

    SCHEDULE PERFORMANCE INDEX (SPI) – the ratio of work performed (earned value or BCWP) to work scheduled (planned value or BCWS).

    COST PERFORMANCE INDEX / INDICATOR (CPI) – the ratio of earned value to actual costs (CPI = BCWP/ACWP). A value greater than 1 indicates that costs are running under budget. A value less than 1 indicates that costs are running over budget. Often used to predict magnitude of a possible cost overrun by dividing it into the original cost estimate (original cost estimate / CPI = projected cost at completion).
  3. 0
    Rejo Poothokaran ·
    Thanks to all