Guys

can anyone point me to the right direction for doing the quickest way of modifying logic relationships? Appreciate you help...

2 replies

Oldest first
  1. 0
    Muhammad Zeeshan Khan ·
    When ever you modify logic its a good practice to keep a back up first
    Check the critical patch does it effect the logic
    Check the logic means construction should be done before engineering design
    Check the float
    Check the lag
  2. 0
    Christian Adrian De Vera ·
    I’ve found a useful approach using the search tool, not quite the way I have in mind but it will do for now...