Earned Hours Calculation
In the Open Standard
Milton MaindonaldMember for 19 years 3 months
- Created
- 2
- 1
0
Following my weekly updates I run a report to monitor the performance of our Construction Teams and present the findings to Management.
While doing last weeks updates I did a audit on the "Earned Hours" (Achieved Labor Units) and found that I was short of 18 hours from a weekly total of 36 from 1 man for a week.
I update by percentage complete.
I have Duration Type - Fixed Duration & Units
I have % Complete Type - Duration
Can anyone advise as to why the system is not correctly calculating the difference between actual and remaining
and to give me some idea as how to fix my problem?
Thanks for your interest,
Milton.
While doing last weeks updates I did a audit on the "Earned Hours" (Achieved Labor Units) and found that I was short of 18 hours from a weekly total of 36 from 1 man for a week.
I update by percentage complete.
I have Duration Type - Fixed Duration & Units
I have % Complete Type - Duration
Can anyone advise as to why the system is not correctly calculating the difference between actual and remaining
and to give me some idea as how to fix my problem?
Thanks for your interest,
Milton.
2 replies
Oldest firstLog in or join to reply