Dear Members,
Recently I Installed P3 in my laptop (Dell,which has vista). But when i try to open any project it is showing that "Could not open target project" or some times it is showing "Could not open Read only files". Can anyone please suggest me whether i should install any drivers for supporting primavera in vista.
Please advise.

1 reply

Oldest first
  1. 0
    Pranab Kumar Deb ·
    Hello Mohammad,

    YOUR P3WIN file must be loaded in the program files , remove 3 and reinstall in a location where p3 is able to write files to, vista does not let any program to write files into the program files.

    regards

    deb

Log in or join to reply