Skip to content

Inaccurate Total Float Calcs

Beth SpiveyMember for 19 years 9 months
Created
6
1
0
Newly created production scheduler position in fabrication. They had a basic schedule in Microsoft Project that I converted into P3. When I created the project I let it just default to the date P3 wanted in project overview as this project never ends (hopefully). I have all correct logic and durations. For some reason only a few of the activities in each job are picking up that default date of the project must finish by in project overview and giving me float of (example)1,956 hrs. when the rest show 20 hrs. I went to tools/schedule/options to check float calc and I changed it from critical to finish. F9 and still no change. I could understand it picking up that odd date it has no pred/succ. Only thing is that some are being worked out of sequence but I don’t remember having it effect before.

Any help is greatly appreciated! Beth

6 replies

Oldest first
  1. 0
    Anoon Iimos ·
    please go to other threads (i don’t know the link), "favorite feature in P3e/P6"
  2. 0
    Dieter Wambach ·
    Beth
    Some time ago we had a similar situation and couldn’t solve it the direct way. But when we imported MSP into P6, then exported into P3 it was ok. Honestly, I don’t know why.
    Regards
    Dieter
  3. 0
    Beth Spivey ·
    Dieter,

    Thanks for your reply. I do not have access to P6. I have noticed that my new projects are fine so it must something I cannot affect. Thanks again.

    Beth
  4. 0
    Sajid Balma ·
    The most probable answer of odd floats in the programme is CONSTRAINTS. Check if you have hard constraints assigned to those activities.
  5. 0
    Beth Spivey ·
    No constraints..already checked that. Since it is picking up the project overview will finish date, I am with Dieter that is some issue between MPP and P3. New projects I entered myself I have no issues only the ones I imported from Project. Thanks for the help. Beth
  6. 0
    Alexandre Faulx-Briole ·
    Beth,
    the P3 "mpx-to-P3" engine does not fully understand the data that MS Project has sent to its mpx file
    almost every time you will import into P3 a MPP file you will have such errors
    Paul Harris recommends to export the MSP file to an Excel worksheet or a dBase file then to import this file into P3.
    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?