In P3, I have an activity that has already started and progressed 10% to date. I put a suspend date on the activity for 17th Dec 2008 and resume date for 10th Feb. 2009, but it appears to be suspending the activity from ‘time now’. I was expecting to the activity to be active from time now to 17th Dec, then suspended between 17th dec and 10th feb 09. Anyone experienced this before? Any clues?