Skip to content

Importing % Progress from Old Schedule to New Schedule

Jun GallardoMember for 18 years 6 months
Created
2
1
0
In P3, can anyone teach me how to import % progress on all activities of my old schedule to my new schedule. Regards.

2 replies

Oldest first
  1. 0
    Brennan Westworth ·
    two ways i can think of are to use export import or target update

    export import

    1. back up both schedules

    2. open the old schedule and to go tools, project utilities, export

    3. add a new specification

    4. in the content tab include only activity ID and % complete (you might also want remaining duration)

    5. in the format tab I usually use .DBF you can keep the file name C:\P3WIN\P3OUT\P3 if its just a 1 off.

    6. leave selection blank for all activities or set up a filter for the activities you want and click RUN

    7. open the new schedule

    8. go to tools, project utilities, import

    9. add a new specification

    10. enter the path to your file (C:\P3WIN\P3OUT\P3.DBF)

    11. cross your fingers and click RUN


    or u could use Target update

    1. back up both schedules

    2. Open the old schedule

    3. go to tools, project utilities, targets and set the new schedule as a target.

    4. select the new schedule and click the update button. You may need to try this a couple of times with different options selected in the update target dialogue box



    HTH
  2. 0
    Jun Gallardo ·
    Brennan,

    It worked. Thank you.


    Jun

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?