Small Building Projects

Ahmed KhanMember for 17 years 10 months
Created
3
1
0
Hi Planners,

Could any one plz advise me the sequence of activities for a small project for 2400 Sq Ft. (40’x60’) includes the 20 columns (RCC) & Bugdet is around 12 Lakh INR

I am finding the dificulty for making the activity cycle for the above. Basically worked in a huge projects.

If any one have means glad to forward me at "onlyazeem4u@gmail.com"

Thanks

3 replies

Oldest first
  1. 0
    Anoon Iimos ·
    1. Preliminaries (including mobilization)
    2. Layout (Survey)
    3. Earthworks
    4. Concrete Works
    4.1 Foundation
    4.2 Columns / Beams
    4.3 Slabs
    5. Architectural Works
    6. MEP Works
    7. Fit-out
    8. Close-out

    for task sequencing, you can define it in your schedule
  2. 0
    Ahmed Khan ·
    Thank U Mr. Anoon Iimos,

    I am expected for the detailed sequence of activities..

    Regards

    Maask
  3. 0
    Tommy Nug ·
    Hi Maask,

    Could you provide me some overviews of the project? I shall help you to work out the schedule.

    Cheer,

    Tom