Man power histogram
In the Open Standard
Carlos DominguezMember for 17 years 11 months
- Created
- 0
- 2
0
hello ppp’s
the question i have is in P3V5
when i use the histogram chart below and i calculate my average for men in this view, and my average to calculate is 24hrs and it shows me 12 men for example, in my user preferences if i change that to 24hrs does that mean that the men are 12 men for the 24 hour duration or does that mean 12 men for 12hours ? or is it 12 men for 24hours ?
so does that mean 6 men per 12hours and 12 total for 24hours ?
the question i have is in P3V5
when i use the histogram chart below and i calculate my average for men in this view, and my average to calculate is 24hrs and it shows me 12 men for example, in my user preferences if i change that to 24hrs does that mean that the men are 12 men for the 24 hour duration or does that mean 12 men for 12hours ? or is it 12 men for 24hours ?
so does that mean 6 men per 12hours and 12 total for 24hours ?
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?