Predessor Column With Lag/Lead Information

Md Ariff Md ThayoobMember for 21 years 5 months
Created
1
1
0
Hello PPP’s

Can anyone tell me is Primavera version 3.1 and higher able to show the lag/lead information in the Predessor column in addition to the predessor activity as in Microsoft Project, e.g. activity 1SS+5 days.

I have a Word attachment to further illustrate the MS Project screen referred to if you could provide your e-mail.

In the above e.g. the lag information is +5 days to the start to start relationship but unfortunately I could not indicate that in Primavera Predessor’s column. I only managed to make Primevera show the predessor activity only without the lead/lag information i.e. in this example "activity 1" (for illustration purposes) only.

I belong to those few who like to show the activity links in column form as well in addition to graphical representation.

Thanks

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    hello mohammed,
    The Pred and Succ fileds in P3 only display the Activity ID.
    You might use the SR-06 report to show the lead and lag too.
    All the best,
    Alexandre