how to fix the negative float in P3.1
In the Open Standard
Genc KrasniqiMember for 17 years 8 months
- Created
- 4
- 3
0
Hi everyone.
I started using primavera only recently and not very happy. I input all the activities and once I clicked schedule it shows that there is 200 days plus negative total float. What am I doing wrong? I check the early start and it shows a current date but then the late start right underneath it is a year old, i.e. 2008. What can I do to fix it? any assistance appreciated. Thank you very much, Genc
I started using primavera only recently and not very happy. I input all the activities and once I clicked schedule it shows that there is 200 days plus negative total float. What am I doing wrong? I check the early start and it shows a current date but then the late start right underneath it is a year old, i.e. 2008. What can I do to fix it? any assistance appreciated. Thank you very much, Genc
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?