Error In Primavera P3 3.1 on Sony Vaio Machines
In the Open Standard
Kafo SouqMember for 17 years 7 months
- Created
- 9
- 4
0
Dear All
I have bought a new Laptob (Sony Vaio VGN-SR26) Dual Core Processor and running genuine MS Windows Vista Business Edition and It comes bundled with an XP (Win XP Pro with SP3) CD also
--- The Begining
Now For starters I downgraded the machine using the CD and Installed my trusted version of P3.1
The problem is that once I open filters and Go through one filter and start picking values (Like Name of Engineer under resources) The Entire P3 Quits and an error message of "Unable to lock Password" pops up ,
I tried to install SP3 pack for Primavera and that didn’t solve the problem so I reinstalled Vista and Regained the riginal factory settings from the Original Packup CDs and I installed Primavera
Only This time to meet new Error Message once I go an Pick Filters and Fiddle through the values
1- First P3 Freezes and
2- An Error Message appears and Says (wowexec caused an acess violation in ntvdm.exe at 0x0edad64d) followed by
3 - Another Error Message that Says (NTVDM.EXE had stopped wrking and needs to be terminated)
4- Some other filters give me a "KERNEL32.DLL Error first and Thn Error 3 Apperas (the NTVDM.exe one)
------------------------
Now I rang sony for this and Thy said that the machine is fine and no problems had been sighted for 16bit applicatons on their machines
The Net is empty on this regards, going through the faults on google some topics suggest that P.3.1 Doesn’t go will with Dual Core Machines
Some Refere WOWEXEC/KERNEL32.DLL/NTVDM.EXE errors as registery errors
Some Refere to the ABove errors as caused by a violation to DOS emulation attempted to be accessed using Windows NT
Primavera UAE tells me with a cold blood that they don’t support P3.1 anymore and they can’t help me with this
------------
For God’s Sake all what am asking for is P3 to run normally on this machine (It is a very expensive machine and I need Primavera to work on)
Any Solutions my fellow planners ?
Help Please and sorry for the long post
Yours Truly
I have bought a new Laptob (Sony Vaio VGN-SR26) Dual Core Processor and running genuine MS Windows Vista Business Edition and It comes bundled with an XP (Win XP Pro with SP3) CD also
--- The Begining
Now For starters I downgraded the machine using the CD and Installed my trusted version of P3.1
The problem is that once I open filters and Go through one filter and start picking values (Like Name of Engineer under resources) The Entire P3 Quits and an error message of "Unable to lock Password" pops up ,
I tried to install SP3 pack for Primavera and that didn’t solve the problem so I reinstalled Vista and Regained the riginal factory settings from the Original Packup CDs and I installed Primavera
Only This time to meet new Error Message once I go an Pick Filters and Fiddle through the values
1- First P3 Freezes and
2- An Error Message appears and Says (wowexec caused an acess violation in ntvdm.exe at 0x0edad64d) followed by
3 - Another Error Message that Says (NTVDM.EXE had stopped wrking and needs to be terminated)
4- Some other filters give me a "KERNEL32.DLL Error first and Thn Error 3 Apperas (the NTVDM.exe one)
------------------------
Now I rang sony for this and Thy said that the machine is fine and no problems had been sighted for 16bit applicatons on their machines
The Net is empty on this regards, going through the faults on google some topics suggest that P.3.1 Doesn’t go will with Dual Core Machines
Some Refere WOWEXEC/KERNEL32.DLL/NTVDM.EXE errors as registery errors
Some Refere to the ABove errors as caused by a violation to DOS emulation attempted to be accessed using Windows NT
Primavera UAE tells me with a cold blood that they don’t support P3.1 anymore and they can’t help me with this
------------
For God’s Sake all what am asking for is P3 to run normally on this machine (It is a very expensive machine and I need Primavera to work on)
Any Solutions my fellow planners ?
Help Please and sorry for the long post
Yours Truly
9 replies
Oldest firstLog in or join to reply