how to shedule activities based on resourses

Elnur GanbarovMember for 17 years 7 months
Created
2
1
0
Please help me
how to shedule activities based on resourses
for example i have 200 mhr available per day

2 replies

Oldest first
  1. 0
    Kafo Souq ·
    Dear

    Simply set the resourecs as driving

    (Driving resources are those that control the duration of the activity only based on their availability Max / Min)

    In P3 this is a small tick box at the resources dialog box , just tick driving and there you go

    Now for scheduling : you can either schedule based on resourecs availability or you can even stretch your project and Do a resource leveling to avoid "Resource Histogram Spikes" - i.e. sudden increases / decreases in the budgeted amounts)

    If your resource is money - Selling Price / Revenue Etc- Make sure not to assign any value to the resource until you finish scheduling and you are satisfied with the results and then load you values

    Hope this answered you question
  2. 0
    Elnur Ganbarov ·
    Dear Kafo

    thanks for help specialy for that part

    Now for scheduling : you can either schedule based on resourecs availability or you can even stretch your project and Do a resource leveling to avoid "Resource Histogram Spikes" - i.e. sudden increases / decreases in the budgeted amounts)