Percent weight in Primavera P3 S-curve

Chandan KakatiMember for 18 years 5 months
Created
1
1
0
Can anyone tell me how to assign percent weight for different phase of a project for producing a Project S-curve. I have a percent weight as Engineering:Procurement/Fab:Construction:Commissioning = 25%:15%:55%:5% which I need to assign to each phase S-curve and get a overall Project S-curve. e.g. suppose I have a % complete for engineering as 40%, the contribution it will make to overall progress as 40*25%=10%. Please help its really urgent.

1 reply

Oldest first
  1. 0
    Mimoune Djouallah ·
    hi

    you need to assign a resource, "call it manhour for simplification" to your program,
    let’s say the total budget quantity for your program will be 100 Hours. thus :

    Engineering = 25 hour
    Procurement/Fab = 15 hour
    Construction = 55 hour
    Commissioning = 5 hour


    HTH