starting remaining works program
In the Open Standard
Kumar IMember for 23 years 3 months
- Created
- 2
- 3
0
while preparing a remaining works program,at the data date,many activities are progressing at the same and these activities will be with out predecessors like project commencement which has elapsed much earlier,which may lead to false schedule calculations,what is the remedy for this situation