can I put RD > OD in P3 !

Mimoune DjouallahMember for 20 years
Created
5
1
0
hi dear planners

when i update my program, i have some activities which has RD > OD( updated manually), but i can’t get P3 to show me the total percent complete of the project, it show always zero.

any idea ?

mimoune

5 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    saha mimoune, ouash rak?
    I just faced the same situation today while giving a training session on P3 in Hydra
    I have entered the total percent complete by hand in the Pct field
    is Arzew still fine for you?
    Alexandre ’iskander el dziri’
  2. 0
    Joao Ribeiro ·
    Have you checked the options "Link remainig duration and schedule percent complete" and the ones for summarization?

    HTH
  3. 0
    Mimoune Djouallah ·
    escander yeah my friend, i am always in arzew, now it become very interesting, many nationalities, we lack only people from Antarctica.

    Joao Reibero, yes of course, this option is off, otherwise i can’t get P3 to show me, RD> OD

    Please can you take a look at this thread and tell me what you think !!

    http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=1&Top=58911&page=2

    thanks very much
  4. 0
    Alexandre Faulx-Briole ·
    Mimoune yâ khô,
    P3 computes Pct to be equal to (OD-RD)/OD and not under 0; therefore, when you enter RD > OD, Pct becomes 0; should you have OD = 3, RD = 4, "new scheduled duration" = 7, you will enter Pct accordingly
    Have a good time in Arzew, I am going back to Paris and be in Algiers again within one month inch’allah
    Alexandre
  5. 0
    Mimoune Djouallah ·
    thanks really

Log in or join to reply