This may sound stupid ....
In the Open Standard
Carlos AranaMember for 17 years 4 months
- Created
- 6
- 1
0
Hi everybody, I’m new on this forum because I’m migrating from Primavera P6 to Primavera P3. Oracle does not provide support for P3 anymore, and after many google searches leading directly here, I decided to join your community.
Migrating from P6 to P3 has been a pain. There are things I did in P6 that cannot be done in P3. The strange thing is that, also, there are things that you can do in P3 that cannot be done in P6. After this brief introduction, I’m having some issues, hope someone can give me some advice:
1. The first activity in the project I’m managing has negative total float of -657 days. There are no constrained activities. What could be the reason?
2. Is there a way to change the project start and finish dates in P3? Where in P3 can I see these dates?
Migrating from P6 to P3 has been a pain. There are things I did in P6 that cannot be done in P3. The strange thing is that, also, there are things that you can do in P3 that cannot be done in P6. After this brief introduction, I’m having some issues, hope someone can give me some advice:
1. The first activity in the project I’m managing has negative total float of -657 days. There are no constrained activities. What could be the reason?
2. Is there a way to change the project start and finish dates in P3? Where in P3 can I see these dates?
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?