unable to load resources

Irfan KhanMember for 17 years 3 months
Created
1
2
0
hi to all,

i m new in planning, now i m working with soil improving & grading package Projects.

i would like to ask that how to load resource in that schedule.


thanks .....

1 reply

Oldest first
  1. 0
    Shah. HB ·
    1. Define name of the resource you r going to use in your project in Data--> Dictionary

    2.Select your activity and click Ctrl+r to open resource dialog box ,in that drop down the inverted arrow icon and selest the resource you want to assign to activities and plug in budgeted quantities it is preferred than plugging in unit per day option
    Repeat step 2 for the rest of activities

Log in or join to reply